Work on Dike 2 at Bersimis II began in fall 2024 and continued into 2025, including the construction of watertight earthfill structures. Watertightness was provided by a five-layer geosynthetic system:
- Two geotextile layers
- Two geomembrane layers
- One geosynthetic drainage layer
The lined sections were verified using the water puddle method on the exposed geomembrane and the dipole method on the covered geomembrane.
Date:
2025
Location:
Bersimis II, Quebec
Project type:
Water Management
Client:
Pomerleau
Services:
Water Puddle and Dipole Leak Location
Keywords:
Leak Location, Hydroelectricity, Water Puddle, Dipole, LDPE