Water Puddle and Dipole Leak Location in the New Cell C at ArcelorMittal Contrecœur East, Canada

November 2025
The HDPE geomembrane was first tested using the water puddle method, followed by the dipole method after the protective and drainage layer had been installed. The cell covered an area of approximately 21,000 m2.

Date: 2025
Location: Contrecœur East, Canada
Project type: Industrial Waste
Client: ArcelorMittal Produits Longs Canada s.e.n.c.
Services: Water Puddle and Dipole Leak Location
Keywords: Leak Location, Water Puddle, Dipole, HDPE, Mittal, Steel